Confidential — internal case file

The "Technical Alignment" Record — PowerTree · Arctech · AFRY

Deep-dive: who engineered and selected the tracker and module, and when — November 2023 to July 2024

A single email thread family — "Technical Alignment Group A", later "Technical Alignment Projects Power Tree – IEnergía" — documents the entire pre-contract engineering of these plants. It shows the Owner (PowerTree), the tracker manufacturer (Arctech) and the Owner's engineer (AFRY) selecting, engineering and putting the tracker system into production months before any EPC Contract was signed, with iEnergia absent from the thread until mid-2024 — after signature.

Why this thread matters

It answers the Notice's central allegation

The Owner's Notice attributes the defects to the "Contractor's defective design or engineering (including review and validation of third party and vendors design and specifications)". The Technical Alignment record shows the design and engineering of the tracker system — including its interface with the module — was performed between PowerTree, Arctech and AFRY, on PowerTree's project account, before the Contractor had a contract. The "third party" whose design was involved is identified: AFRY (Patrick Furrer, later Jorge Saavedra), engaged on the Owner's side.

Who was on the thread

PowerTree (Owner)

  • Joep Thomassen — Technical Director (thread owner)
  • Francisco Promis
  • Rosalía Méndez — then rosalia.mendez@power-tree.co.uk; the same person who served the July 2026 Notices from infrastrutture.eu
  • Hugo Olivares

Arctech (tracker manufacturer)

  • Arturo Quinteros — Technical Sales Engineer LATAM
  • Alejandro Deulofeu — Project Engineer LATAM
  • Alejandro Silva · Fernando Pinto · Cristian Valenzuela

AFRY (Owner's engineer)

  • Patrick Furrer — on thread Nov 2023 – Jan 2024
  • Jorge Saavedra — on thread from Jan 2024 onward

iEnergia (Alex Carthew, then Project Manager at iEnergia; Sara Barriuso, Project Engineer) appears on the thread only from May–June 2024 — after the EPCs were signed.

The pre-contract chronology, message by message

Contract dates, for contrast

Angol EPC signed 10 April 2024 · Los Sauces I & II 19 April 2024 · Falcon & Dinamo 16 May 2024. Everything above precedes all of them. Corroborating Dropbox record: Arctech GA drawing GA-2023112206-CL-POWER TREE-Angol Solar I (Nov 2023) and Preliminary Foundation Design dated 19-12-23 stating "Client: PowerTree" and specifying the SkyLine II 1V64 — see Documents.

Mid-2024: iEnergia joins — and immediately starts reporting errors

Once the EPCs were signed, iEnergia (Alex Carthew, Sara Barriuso) joined the thread. Its first documented acts were to question and correct the Owner-supplied Arctech engineering — exactly the conduct Clause 2.15(c) rewards:

What this record proves — and what it does not

PROVEN

  • The tracker system was selected, engineered and in production (piles, China) on the Owner's orders by January 2024 — before any EPC.
  • The module datasheet was delivered by PowerTree to Arctech on 27 Nov 2023 — the module–tracker pairing was the Owner's act.
  • AFRY (Patrick Furrer → Jorge Saavedra) was the engineer on the Owner's side of that process.
  • PowerTree issued the purchase orders and "filled the technical sheets … for each project".
  • iEnergia was not a participant in the selection or pre-contract engineering.
  • Post-contract, iEnergia notified technical errors in the Owner-supplied engineering in writing (drawing inconsistencies 4 Jun 2024; torque-tube geometry 28 Jun 2024) — conduct within Clause 2.15(c).

NOT (YET) PROVEN

  • That iEnergia raised a written concern specifically about module format/size. No such record has been located in the mailbox or Dropbox. The purlin / 1400 mm hole-spacing / rivet-fastener compatibility point was raised by M. Troncoso (the Owner) on 26 May 2026 — not by iEnergia. Until sourced, this must not be asserted externally.
  • The precise date PowerTree/Trina executed the module supply contract (pre-EPC selection is proven; the purchase paper sits on the Owner's side).

Prepared text — for use in correspondence

Drafted for insertion into a letter or memorandum. Every sentence below is supported by the record on this page. English; formal register.

The design and engineering of the tracker system installed at the Projects — including its pairing with the PV module — was performed before the EPC Contracts existed, by and on behalf of the Owner. The contemporaneous record ("Technical Alignment Group A", November 2023 – January 2024) shows Arctech Solar performing the tracker engineering for the Owner's project group under the direction of PowerTree LTD's Technical Director, with AFRY acting as the Owner's engineer, and with no participation by the Contractor.

By 27 November 2023, the Owner had delivered to Arctech the geotechnical reports, pull-out test results, topography, final layouts and — significantly — the datasheet of the PV module with which the tracker was to be configured. By 22 January 2024, Arctech had issued the bills of materials for the tracker posts of the first six projects to the Owner for review; by 26 January 2024, the Owner had placed and was auditing six purchase orders against Arctech's foundation calculations; and on 30 January 2024, Arctech confirmed to the Owner that those same values had been "sent to our manufacturing plant for the production of the piles". The first EPC Contract of the affected portfolio was signed on 10 April 2024.

It follows that the selection of the Arctech SkyLine II tracker, the selection of the Trina Vertex module, and the engineering of their combination were acts of the Owner, completed and committed to manufacture months before the Contractor was engaged. The Contractor subsequently procured and installed the equipment the Owner had specified — a specification the Owner then incorporated into the EPC Contract itself at Schedule C-7 (Technical Specifications of Key Components).

For completeness: where, after contract execution, the Contractor identified inconsistencies in the Owner-supplied engineering, it notified them promptly and in writing — including the discrepancy between successive drawing issues and pile distributions (4 June 2024) and the inconsistency of torque-tube lengths between plan and elevation views in the Owner-supplied DWGs (28 June 2024) — and requested the Owner's and Arctech's written clarification in each case, in accordance with Clause 2.15(c) of the EPC Contract.